Project Bid Deadline
6/19/2026
Contact Email
Link / Website
https://securecc.smartinsight.co/#/PublicBidProject/861153
Description
Project Description:
Building 7 was built in 1981, and totals 64, 924 SF. Located at the Salem Campus, this building serves programs for health education, physical fitness, athletics, and other wellness-related programs. The project consists of a full structural, interior, and site renovation.
BOLI commercial prevailing wage rates are a requirement for this project.
Scopes of Work NOT Available to Bid:
This following scope of work have been procured in early bid package 01, 02, and 03 and are no longer available:
1.Fire Sprinklers
2.Plumbing & HVAC
3.Electrical & Low Voltage
4.Roofing
5.Hazardous Material Abatement
6.Structural and Select Building Demolition
7.CIP Concrete (No Site Concrete)
8.Reinforcing Steel – Supply
9.Reinforcing Steel – Install
10.Brick Veener & CMU Masonry
11.Strutral Steel – Supply
12.Structural Steel – Install
13.Rough Carpentry Framing
14.Skylights
15.Earthwork & Utilities
16.Surveying
17.DFH Supply
Scopes of Work Available to Bid:
- Scopes not listed above.
Milestone Dates:
- Job Walk: 06/08/2026 at 10:00 AM
- Outreach Event at College* (Building 7, Room 106): 06/12/2026 at 10:30 AM
- *NOTE: R&C Management Will Also Be At This Event To Discuss All Upcoming Bond Projects At Chemeketa
- Deadline for Bidder Questions: 06/09/2026 at 2:00 PM
- Addendum 1 Package Released: 06/15/2026
- Bids Due: 06/19/2026 at 2:00 PM
- Notices of Intent to Award: 07/27/2026
- Start of Construction (For this Bid Package): 08/01/2026
- Substantial Completion: August 2027
Available Project Information:
The following project documents can be found at www.bremik.com/planroom
- Plans: 100% CD Set, Facet Architects, 5/21/2026
- Specifications: 100% CD Set, Facet Architects, 5/21/2026
- Hazardous Material Assessment: Advantage Environmental, Inc. – See Exhibit J
- Geotechnical Report: Central Engineering Services, 4/07/2026
- Matterport Model
- There is a Matterport Model that is available for assisting in analyzing existing building conditions
- https://my.matterport.com/show/?m=emJpFeoaNe3
Contracting Requirements:
- Wage Requirements BOLI Commercial Prevailing Wages
- Workforce Diversity and Inclusion Requirements: Yes
- This Project is subject to the workforce diversity requirements of ORS 279C.533. Subcontractor shall participate in and comply with Contractor’s Workforce Diversity Plan, including documented outreach, recruitment, and retention efforts directed toward women, minority individuals, and veterans.
- Apprentice Participation & Workforce Training: Yes
- This Project is subject to ORS 279C.533. Subcontractor shall ensure that not less than fifteen percent (15%) of the total labor hours worked in apprenticeable occupations under this Subcontract are performed by apprentices registered in a BOLI-approved apprenticeship program.
How to Submit Pre-Bid Questions:
All questions or substitution requests must be directed to Bremik Construction. Do not contact the architect, owner, or any design consultants directly. Any correspondence not submitted through Bremik Construction will not be answered.
- Send all questions to: Casey Miller, Senior Project Manager (cmiller@Bremik.com), Ryan Pugh, Project Manager (rpugh@Bremik.com), & Bids@Bremik.com
How to Submit a Bid:
Review all provided bid materials. Fill out the Bid Form provided and attach it to your proposal on company letterhead with your bid, clarifications, assumptions and exclusions, and combine into a single .PDF packet.
- Send bids to Bids@Bremik.com