Event Date / Project Bid Deadline
5/6/2026
Contact Email
Link / Website
Description
Project Description:
Building 7 was built in 1981, and totals 64, 924 SF. Located at the Salem Campus, this building serves programs for health education, physical fitness, athletics, and other wellness-related programs. The project consists of the following scope: abatement and demolition, structural enhancements, storefront, skylights, earthwork and utility improvements, and site upgrades.
BOLI commercial prevailing wage rates are a requirement for this project.
Scopes of Work Available to Bid:Only the listed scopes of work are available to bid at this time. For more information on future opportunities related to this project, please reach out to Bremik Construction.
This following scope of work have been procured in early bid package 01 and are no longer available:
- Fire Sprinklers
- Plumbing & HVAC
- Electrical & Low Voltage
- Roofing
ONLY the following scopes are available at this time, in this bid package 02. All other scopes of work will be bid out in future bid packages:
1.Hazardous Material Abatement
2.Structural and Select Building Demolition
3.CIP Concrete (No Site Concrete)
4.Reinforcing Steel – Supply
5.Reinforcing Steel – Install
6.Brick Veener & CMU Masonry
7.Strutral Steel – Supply
8.Structural Steel – Install
9.Rough Carpentry Framing
10.Skylights
11.Earthwork & Utilities
12.Surveying
Milestone Dates:
- Job Walk 04/21/2026 at 1:00 PM
- Outreach Event at College* (Building 7, Room 106) 04/28/2026 at 10:30 AM
- *NOTE: R&C Management Will Also Be At This Event To Discuss All Upcoming Bond Projects At Chemeketa
- Deadline for Bidder Questions: 04/24/2026 at 2:00 PM
- Addendum 1 Package Released 05/01/2026
- Bids Due 05/06/2026 at 2:00 PM
- Notices of Intent to Award 05/29/2026
- Start of Construction 6/15/2026
- Substantial Completion August 2027
Available Project Information:
The following project documents can be found at www.bremik.com/planroom
- Plans: Permit/CD Progress Set, Facet Architects, 3/26/2026
- Specifications: Permit Set, Facet Architects, 3/26/2026
- Hazardous Material Assessment: Advantage Environmental, Inc. – See Exhibit J
- Geotechnical Report: Central Engineering Services, 4/07/2026
- Matterport ModelThere is a Matterport Model that is available for assisting in analyzing existing building conditions
- https://my.matterport.com/show/?m=emJpFeoaNe3
Contracting Requirements:
- Wage Requirements BOLI Commercial Prevailing Wages
- Workforce Diversity and Inclusion Requirements Yes
- This Project is subject to the workforce diversity requirements of ORS 279C.533. Subcontractor shall participate in and comply with Contractor’s Workforce Diversity Plan, including documented outreach, recruitment, and retention efforts directed toward women, minority individuals, and veterans.
- Apprentice Participation & Workforce Training Yes
- This Project is subject to ORS 279C.533. Subcontractor shall ensure that not less than fifteen percent (15%) of the total labor hours worked in apprenticeable occupations under this Subcontract are performed by apprentices registered in a BOLI-approved apprenticeship program.
How to Submit Pre-Bid Questions:
All questions or substitution requests must be directed to Bremik Construction. Do not contact the architect, owner, or any design consultants directly. Any correspondence not submitted through Bremik Construction will not be answered.
- Send all questions to: Casey Miller, Senior Project Manager (cmiller@Bremik.com), Ryan Pugh, Project Manager (rpugh@Bremik.com), & Bids@Bremik.com
How to Submit a Bid:
- Review all provided bid materials. Fill out the Bid Form provided and attach it to your proposal on company letterhead with your bid, clarifications, assumptions and exclusions, and combine into a single .PDF packet.
- Send bids to Bids@Bremik.com
