Be a bridge to change. Become a NAMC-Oregon Member Today!

Project Bid Deadline

5/13/2026

 

Contact Email

maize@faisonconstruction.com

 

Link / Website

https://www.dropbox.com/scl/fo/ts41uzijr1kfdklguwwlb/ADhN7WBDBujuuEGmefM-e6A?rlkey=trajhbp227ofjk1jidh9fl25y&e=1&st=3bbbtuzc&dl=0

 

Description

The work to be completed consists of construction of 1350 LF of street reconstruction and improvements including 5ft sidewalk, ADA ramps. driveway approaches, in-place pavement pulverizing, grind and overlay existing pavement, new street pavement sections, a vegetated infiltration planter, a vegetated water quality basin, signage and striping, CIPP lining of existing 8-inch sanitary sewer, electrical undergrounding, street lights, relocation of existing fences and gates, french drain, and storm water infrastructure.

 

Marketing Material

DunbarAve_ITB.pdf

https://www.faisonconstruction.com/
https://www.faisonconstruction.com/